The cube test is the everyday measure of concrete quality on Indian construction sites. Cubes are cast from the same concrete placed in the structure, cured, and crushed at set ages to confirm that the concrete meets its specified grade. The method of test is given in IS 516; sampling and acceptance criteria come from IS 456 and project specifications. This guide walks through the test as it is done on a compression testing machine (CTM).

Moulds and specimens

The standard cube for most concrete is 150 mm. Smaller 100 mm cubes may be permitted where the maximum aggregate size allows. Moulds should be rigid, with faces flat and square within the tolerances of the standard, and the joints tight so mortar does not leak. Worn or distorted moulds produce cubes with uneven faces, which crush at lower loads.

See concrete cube moulds for compression testing.

Casting and curing

  1. Sample concrete as specified, from the batch being placed.
  2. Oil the mould lightly and fill it in layers, compacting each layer by tamping or vibration as the standard specifies.
  3. Finish the top surface level with the mould.
  4. Store the filled moulds undisturbed, protected from drying and extreme temperature, for the initial period before demoulding (typically about 24 hours).
  5. Mark each cube and transfer it to a water curing tank at the controlled temperature set by the standard (27 ± 2 °C) until testing.

Testing on the CTM

  1. Remove from water shortly before the test and wipe off surface water and grit. Test the cube in a surface-dry condition without letting it dry out.
  2. Measure the cube dimensions and, where required, weigh it.
  3. Clean the platens and place the cube centrally, with the load applied to two opposite faces that were against the mould sides, not to the trowelled top and the bottom.
  4. Seat the cube using the spherically seated platen so it bears evenly.
  5. Load at the specified rate without shock, increasing continuously until failure. IS 516 specifies a stress rate of 14 N/mm² per minute (about 5.25 kN/s for a 150 mm cube).
  6. Record the maximum load and note the mode of failure.

Calculating and reporting

Compressive strength = maximum load ÷ cross-sectional area of the loaded face, expressed in N/mm² (MPa). The result for a sample is normally the average of the cubes in a set, provided individual results fall within the variation the standard allows; outliers must be investigated.

Report item Example of content
Identification Cube ID, location of pour, date of casting
Age at test 7 days, 28 days, or as specified
Dimensions and mass Measured values
Maximum load kN
Compressive strength N/mm², each cube and average
Failure type Satisfactory or unsatisfactory, with notes

Failure patterns

A satisfactory failure shows roughly equal cracking on all four exposed faces, leaving a double-pyramid shape. Cracking on one side only, or splitting with a vertical crack through the cube, can indicate eccentric loading, non-parallel faces, worn platens or a seized spherical seat.

Common causes of low or scattered results

  • Poor compaction, leaving voids
  • Cubes allowed to dry before testing or cured at the wrong temperature
  • Loading the trowelled face
  • Loading too fast or with shock
  • Worn moulds or platens
  • An uncalibrated machine; CTMs should be verified to IS 1828 (Part 1) at the required interval

Choosing a CTM

For cube testing, consider capacity for your highest-grade concrete, the clearance and platen size, pace-rate control, data recording and the calibration support available. Akuracy offers a digital compression testing machine and a cube testing machine.

Looking after the CTM

Machine condition directly affects cube results. Keep the platens clean and check them for wear and hollows. Make sure the spherical seat moves freely before loading and locks once the cube is seated. Check hydraulic oil level and leaks, and keep the pace-rate control working so the specified loading rate is achieved without manual adjustment. Clear concrete debris after every test, as fragments on the platen create point loads on the next cube.

Using cube results

Cube results show whether the concrete supplied meets the specified grade. Early-age results, such as 7 days, give a first indication; acceptance is usually based on 28-day strength assessed against the criteria in IS 456 and the project specification. Plotting results over a project helps the contractor and the ready-mix supplier spot trends in quality before they become a compliance problem. When results are low, check the testing and curing records first, since many apparent failures come from sampling or curing problems rather than the concrete itself.

Key takeaways

  • Use true, rigid moulds and compact cubes properly.
  • Cure in water at the specified temperature until testing.
  • Load the moulded faces at the IS 516 rate, without shock.
  • Record failure type, and check curing and testing records before blaming the concrete.

Frequently asked questions

Why load the cube on the moulded faces?

The moulded side faces are flat and parallel. The trowelled top is not, and loading it causes uneven stress and lower strength.

Why test cubes in a surface-dry condition?

Strength depends on moisture state. Testing saturated surface-dry cubes straight from curing gives consistent, comparable results.

What rate of loading does IS 516 specify?

IS 516 specifies 14 N/mm² per minute. For a 150 mm cube this is about 315 kN per minute.